This project includes multiple recommended improvements from the City’s latest stormwater master plan along Washington Dam Road. Upsizing these storm drain lines and adding a detention pond will help increase the capacity of the system to better handle large rainfall events.
Project Description
The project includes four separate recommended improvements from the City’s latest stormwater master plan:
Schedule
Design: Summer/Fall 2021
Construction Commencing: Late 2021
Construction Completion: Spring 2022
Updates
7-21-2022 Design is complete. Working on easements.