3090 S and Washington Fields Road

Project Information

The Design of this intersection has been completed and materials have been ordered. Construction will begin when materials arrive.

6/16/22 The concrete bases for the signals have been poured. After the proper curing time the installation of the signal will continue. All materials have been secured and the signal is under construction.

7/1/22 Vertical poles and street lights are installed. The street light will be turned on with the traffic signal. The remaining parts of the signal will be installed within the next few weeks.